OpenBOM Change Management User Manual: Best Practices Guide
Welcome to the End User Manual for managing change processes, specifically Change Requests and Change Orders, in OpenBOM. This manual aims to provide you with a comprehensive understanding of the change management process within OpenBOM, along with step-by-step instructions and best practices for efficient execution.
The Change Process plays a crucial role in the New Product Development (NPD) or New Product Introduction (NPI) process. As products evolve from concept to production, changes are inevitable to address improvements, corrections, or updates. Efficiently managing these changes ensures product quality, reduces time-to-market, and enhances overall project success.
In OpenBOM, the Change Process consists of two primary components: Change Orders (CO) and Change Requests (CR)
Change Orders: Change Orders enable the consolidation of one or multiple Change Requests into a single formal process. This grouping streamlines the management of related changes, allowing for cohesive review and approval. Change Orders ensure that all modifications are coordinated and implemented effectively, minimizing disruptions to the project workflow.
Change Requests: Change Requests are initiated to propose modifications to the Bill of Materials (BOM) or related documents. These modifications can include updates to part information, revisions, vendor changes, or any other alterations required. Change Requests provide a structured approach for documenting, reviewing, and approving proposed changes before implementation.
The output of a Change Request is an Item Revision
(https://help.openbom.com/my-openbom/change-management-and-revision-control)
Let’s dive into the change process using the ” Door Handle Sub-Assembly BOM” example with two scenarios:
Example 1:
Material Change – Updating the Material for the “Handle ” component (STL-004) from “Brass” to “Steel” as per a customer request
Example 2:
Vendor Change – Updating the vendor for the “Handle” component (STL-004) from “DoorKnob Inc.” to “KnobMaster Co.” for better pricing.
Identify the need for changes in the BOM, such as updating the vendor and material details for a component.
Fig 1– Check for Change Request (Catalog)
Fig 1a – Check for Change Request to initiate Revision
3. Initiate Change Request:
Fig 2 – Access and Create Change Request from Context Menu
4. Approving the Change Request (Change Administrator or Based on the Privileges):
Fig 2a – Access and Create Change Request from Revision Dropdown Menu
Fig 3 –Change Request Approved and Revision Created
5. View Changes:
Fig 4 – Change Request History
6. Making Changes to the Component (“Handle”):
7. Update BOM Table:
Fig 5 – Change Item Properties – Material and Vendor
8. Creating Change Request for BOM Changes:
Fig 6 – Change Request Created Successfully
Approval Workflow
1. Review Changes:
2. Release Changes:
Fig 7 – Change Request Approved and Released
Fig 7a – Change Request Review, Approve and Release
1. Navigate to BOM or Catalog.
2. Locate and click on the Door Handle Sub-Assembly BOM from the list.
3. Initiate Change Order for “Material and Vendor Change”
Fig 8 – Create Change Order
4. Notification will be sent to the Change Administrator
Fig 9 – Create Change Order Notification
5. Update Material and Vendor Information
Fig 10 – Make Property Changes and initiate Create Request
6. Select Item Revision
7. Create Change Request
Fig 11 – Create Change Request with Change Order
8. Review and Approval of Change Order
Fig 12 –Change Order Approval
Fig 13 – Change Order Approval Notification
Fig 14 – Change Request set to Release with new Item Revision
Users appointed to the same change order can perform approval via collaborative workflow change order capabilities. – collaborative approval. In this screen, everyone can see the status of approval and can involve all stakeholders who need to review and approve the change order, including the Engineer, Manager, and any other relevant team members. During the collaborative approval process, each person can provide feedback and suggest changes to the change order. Once all stakeholders have reviewed and approved the change order, the final approval and revisions creation will happen.
The BOM compare feature enables the comparison of two distinct versions of a single bill of materials, providing a comprehensive analysis of their differences.
Fig 15 – BOM Compare Menu
3. Open Comparison Window
4. Enter Part Numbers and Choose Revisions
5. Initiate Comparison
Fig 16 – BOM Compare Result
6. Review Comparison Results
Fig 17 – BOM Compare Differences
7. Identify Differences – Differences between the BOMs will be highlighted in color, making it easy to spot changes and discrepancies.
Change Request
Change Order
BOM Comparison
1. How can I ensure my Change Request is understood?
Provide clear and specific descriptions to avoid any confusion among stakeholders.
2. Can I include multiple changes in one Change Order?
Yes, grouping similar changes in a single Change Order is recommended for efficiency.
3. How often should I review Change Reports?
Regularly reviewing and archiving Change Reports helps maintain an accurate audit trail.
4. How do I ensure accuracy in BOM Comparison?
Always double-check the selected BOMs and revisions to ensure accurate comparison results.
Congratulations on completing Change management with OpenBOM PLM. Effective change management is essential for ensuring the success of product development projects. By following the structured Change Process in OpenBOM, you can efficiently manage modifications to your Bill of Materials, streamline approval workflows, and maintain project integrity throughout the NPD/NPI process. This End User Manual serves as a guide to navigating the Change Process in OpenBOM, empowering you to drive positive outcomes and enhance project efficiency.